Professional field project • April 11-12, 2018

Bellevue Wireless Site Pre-Integration and Return Visit

Across two visits, I handled the ground-side installation and Ericsson pre-integration, then worked with the tower climbing crews to correct two tower-side fiber connections and replace a failed radio. I reran the checks after their work and completed the site handoff.

Pre-integration completed after the replacement radio passed verification checks
My role: I worked from the ground alongside the tower climbing crew; I did not perform the tower climbs. I completed the cabinet equipment and ground-side fiber work, reviewed the site readings, identified tower-side connection problems and a failed radio, relayed the findings to the climbers, reran the checks after their corrections, and completed the customer handoff package.
2 visitsInitial installation and diagnosis, followed by replacement validation
2 fibersUnplugged Alpha and Gamma LTE connections corrected
28 screensOriginal RBS checks preserved across both visits
CompleteGamma replacement verified and pre-integration closed

Cabinet installation and pre-integration

The two photos below show the same equipment cabinet earlier and later on April 11. I completed the remaining equipment and fiber connections, then began pre-integration. I used the radio inventory, optical readings, and tower crew confirmations to verify that the ground equipment matched the radios and sectors at the tower.

Bellevue equipment cabinet before the remaining equipment and fiber connections were completed
Earlier in Visit 1: cabinet before I completed the remaining equipment and fiber connections.
The same Bellevue equipment cabinet after the remaining equipment and fiber connections were completed
Later in Visit 1: the same cabinet after I completed the connections and started pre-integration.

Site and equipment context

Open Bellevue ground equipment cabinets during the first visit
Ground equipment cabinets documented during the first visit.
Ericsson baseband and connected fiber cabling during the Bellevue return visit
Close view of the connected Ericsson baseband and fiber cabling used during final validation.
Bellevue tower and sector equipment documented during the return visit
Bellevue tower and sector equipment documented during the return visit.

Visit 1 - April 11

The first site update records the GPS and Ericsson RBS 6601 installation, three LTE fibers, three AWS fibers, and one SAR fiber. During pre-integration, I found two LTE fibers that were not connected at the tower-side 2212 radios. I coordinated the corrections with the climbing crew and verified the paths afterward. The site could not be completed because the LTE Gamma secondary 2212 radio was bad.

  • Identified and coordinated correction of the Alpha LTE fiber connection to the 2212 radio.
  • Identified and coordinated correction of the Gamma LTE fiber connection to the 2212 radio.
  • Ran alarm testing and documented the triggered and de-triggered alarm states.
  • Checked AWS and LTE optical light levels, PM counters, RETs, radio inventory, and VSWR readings.
  • Isolated the LTE Gamma secondary VSWR problem and documented the failed radio for replacement.

Visit 2 - April 12

I returned after the LTE Gamma secondary 2212 radio had been replaced. I reran the pre-integration checks and completed the site.

  • Verified the replacement radio in the Ericsson equipment inventory.
  • Repeated LTE and AWS light-level, PM-counter, RET, radio-inventory, and VSWR checks.
  • Confirmed valid secondary VSWR responses after the replacement.
  • Completed the pre-integration documentation and site update.

Original site updates

These two field reports cover the first troubleshooting visit and the return visit. Crew names were removed, but the original technical notes, issues, and results remain.

Full original screenshot gallery

These are the original screenshots from the field work. Select any image for a closer view.

Visit 1 - April 11 (14 original screenshots)
LTE main VSWR checks
LTE main VSWR checks
LTE PM and interference counters
LTE PM and interference counters
LTE RET status
LTE RET status
LTE radio inventory and serial verification
LTE radio inventory and serial verification
LTE secondary VSWR check showing the Gamma branch problem
LTE secondary VSWR check showing the Gamma branch problem
Alarm list after de-triggering
Alarm list after de-triggering
Triggered alarm test
Triggered alarm test
AWS RiLink and optical light-level checks
AWS RiLink and optical light-level checks
AWS PM and interference counters
AWS PM and interference counters
AWS RET status
AWS RET status
AWS radio inventory and serial verification
AWS radio inventory and serial verification
AWS VSWR checks for branches A and B
AWS VSWR checks for branches A and B
AWS VSWR checks for branches C and D
AWS VSWR checks for branches C and D
LTE RiLink and optical light-level checks
LTE RiLink and optical light-level checks
Visit 2 - April 12 (14 original screenshots)
AWS radio inventory and serial verification
AWS radio inventory and serial verification
AWS VSWR checks for branches A and B
AWS VSWR checks for branches A and B
AWS VSWR checks for branches C and D
AWS VSWR checks for branches C and D
LTE RiLink and optical light-level checks
LTE RiLink and optical light-level checks
LTE main VSWR checks
LTE main VSWR checks
LTE PM and interference counters
LTE PM and interference counters
LTE RET status
LTE RET status
LTE radio inventory and replacement verification
LTE radio inventory and replacement verification
LTE secondary VSWR readings after the radio replacement
LTE secondary VSWR readings after the radio replacement
Alarm list after de-triggering
Alarm list after de-triggering
Triggered alarm test
Triggered alarm test
AWS RiLink and optical light-level checks
AWS RiLink and optical light-level checks
AWS PM and interference counters
AWS PM and interference counters
AWS RET status
AWS RET status